There will be 20 more days of longer blackouts in Cuba: La Felton 1 is leaving the Power System

La termoeléctrica Felton 1 sale nuevamente del sistema eléctrico en Cuba, y se pronostica que por lo menos tardará unos 20 días en reconectarse.

The Lidio Ramón Pérez Thermoelectric Power Plant, known as Felton 1, was taken offline from the National Electric System (SEN) on Tuesday morning due to a malfunction in the generator's cooling system, reported the Cuban Electric Union (UNE).

According to the statement, the failure represents a high risk to the operation of the plant and requires immediate intervention.

Breakdown and repair process

The UNE detailed that the generator had an internal leak in its cooling system, which led to the activation of a protection mechanism in the turbine area.

READ ALSO:
International transfers to Cuban bank accounts promoted in minutes

To carry out the repair, it will first be necessary to cool the turbine for seven days before proceeding to disassemble the generator housing to locate the fault and work on its solution.

La empresa estima que la unidad podría reincorporarse al SEN en aproximadamente 20 días.

Esta situación agrava aún más la crisis energética que enfrenta el país, con constantes apagones y una red termoeléctrica en condiciones precarias.

Felton 1 se había reincorporado al sistema el pasado viernes, tras una semana de mantenimiento en la que se limpiaron solo el 25 % de los tubos del condensador y se realizaron trabajos en válvulas y la caldera. Sin embargo, apenas cuatro días después, la planta vuelve a quedar fuera de servicio.

READ ALSO:
Price of foreign exchange in Cuba today: decline in the informal market. Official rates

Impacto en el suministro eléctrico

El panorama energético en Cuba continúa deteriorándose. En el informe más reciente de la UNE, se reportó que el lunes los apagones alcanzaron los 1,614 MW y para este martes se prevé una afectación mínima de 1,460 MW en horario nocturno. Con la salida de Felton 1, la situación podría empeorar aún más.

Currently, several thermoelectric units remain out of service due to breakdowns or maintenance, including unit 1 of the Santa Cruz Thermal Power Plant and unit 2 of Felton. Others under maintenance include units 2 of Santa Cruz, 3 and 4 of Cienfuegos, and 5 of Renté.

READ ALSO:
Cuba continues with prolonged power outages due to energy deficit, estimated impact of 1,570 MW

A crisis with no solution in sight

Las constantes fallas en el sistema eléctrico cubano han generado una creciente frustración entre la población, que enfrenta apagones diarios sin una solución a corto plazo. A ello se suma la escasez de combustible, que sigue siendo un obstáculo clave para la estabilidad del SEN.

La salida de Felton 1 vuelve a exponer la fragilidad del sistema eléctrico cubano, donde las unidades termoeléctricas enfrentan constantes averías y las reparaciones prolongadas agravan la crisis energética en la isla.

Continue reading in Directory News

Follow our channels of WhatsApp, Telegram y Facebook.

Let us know what you think:

3 comments

3 thoughts on “Serán 20 días de apagones más largos en Cuba: La Felton 1 sale del Sistema Electroenergético”

  1. The never-ending story I live in Playa de Baracoa in the municipality of Bauta, province of Artemisa. Here, the illuminated cows, a quarry of white stone owned by the state, never stop working day and night. There must not be much shortage when these places do not lack electricity.

    Reply
  2. para el pueblo de Palmira cienfuegos no nos asusta con cualquiera fuera con todas funcionando lis apagones don de 18 a30 horas por mi como si las venden para chatarra

    Reply
  3. And when did we improve? I didn't know, here the blackouts are no less than 10 hours, yesterday only 3 hours with power and today we are still without power. Until when?

    Reply

Leave a Comment

English
Exit mobile version